From hashrate to HPC: tracking the bitcoin miner pivot to AI hosting
Listed bitcoin miners have announced about $126.5 billion of AI and HPC lease value, $80 billion of it in 2026, led by TeraWulf, Hut 8 and Core Scientific.
Key findings
- Seven listed bitcoin miners now report or have announced roughly $126.5 billion of base-term AI and HPC contract value, our sum of company-disclosed figures as of late September 2026.
- About $80 billion of that total, or 63%, was announced in calendar 2026, led by TeraWulf’s $19 billion, 20-year Anthropic lease (July 6) and Core Scientific’s $14 billion, 15-year AMD agreement (July 28).
- Three companies, TeraWulf ($26.8 billion), Hut 8 ($26.6 billion) and Core Scientific ($24.2 billion), account for 61% of the contracted value.
- Powered-shell and colocation leases price at $1.4 million to $2.4 million of revenue per critical IT megawatt per year, against roughly $0.66 million to $1.21 million of gross bitcoin mining revenue per megawatt at late-September hashprice.
- Core Scientific’s all-stock sale to CoreWeave did not close: shareholders rejected it and the merger agreement was terminated on October 30, 2025. CoreWeave remains a tenant on about 590 MW.
- MARA and Bitfarms (rebranding as Keel Infrastructure) had not disclosed a signed AI or HPC lease as of their August 2026 updates.
From hashrate to leases: what has been signed
Pilot hosting deals from 2024 have become the dominant source of contracted revenue for the larger listed miners, and the tenant base has changed. Early contracts were with GPU clouds (CoreWeave, Core42, Fluidstack), often with Google backstopping Fluidstack’s rent. The 2026 vintage is dominated by direct leases with frontier AI labs and investment-grade technology companies on 15 to 20 year terms, several of them unnamed in company filings.
The table lists each significant contract we could verify from company releases, SEC filings or trade press. Values are base-term contract value as disclosed, excluding renewal options. Megawatts are critical IT load unless noted.
| Announced | Miner | Counterparty | Value | Term | MW (IT) | Site |
|---|---|---|---|---|---|---|
| Jun 2024 to Feb 2025 | Core Scientific | CoreWeave (series of contracts) | $10.2B | 12 yr | ~590 | Six sites incl. Denton, TX |
| Dec 23, 2024 | TeraWulf | Core42 (G42) | $1.1B | 10 yr (5 + renewal) | 72.5 | Lake Mariner, NY |
| Aug 14 and 18, 2025 | TeraWulf | Fluidstack (Google backstop, $3.2B total) | $6.7B | 10 yr | 360 | Lake Mariner, NY |
| Sep 25, 2025 | Cipher Digital | Fluidstack (Google backstop, $1.4B) | $3.0B | 10 yr | 168 | Barber Lake, TX |
| Nov 3, 2025 | Cipher Digital | AWS | $5.5B | 15 yr | 300 (gross) | Black Pearl, TX |
| Nov 3, 2025 | IREN | Microsoft (GPU cloud) | $9.7B | 5 yr | 200 | Childress, TX |
| Nov 2025 | Cipher Digital | Fluidstack expansion (Google backstop +$333M) | $0.83B | 10 yr | 39 | Barber Lake, TX |
| Dec 17, 2025 | Hut 8 | Fluidstack (Google backstop; Anthropic partnership) | $7.0B | 15 yr | 245 | River Bend, LA |
| Jan 16, 2026 | Riot | AMD (later expanded to 50 MW) | $0.31B initial | 10 yr | 25 | Rockdale, TX |
| Mar 25, 2026 | Cipher Digital | Unnamed investment-grade hyperscaler | Not disclosed | 15 yr | Not disclosed | Existing Cipher site |
| May 6, 2026 | Hut 8 | Unnamed high investment-grade tenant | $9.8B | 15 yr | 352 | Beacon Point, TX |
| May 8, 2026 | IREN | Nvidia (GPU cloud) | $3.4B | 5 yr | 60 | Childress, TX |
| Jul 6, 2026 | TeraWulf | Anthropic | $19.0B | 20 yr | 401 | Hawesville, KY |
| Jul 14, 2026 | CleanSpark | Unnamed investment-grade technology company | $6.6B | 20 yr | 175 | Sandersville, GA |
| Jul 20, 2026 | Hut 8 | Same Beacon Point tenant, phase 2 | $9.8B | 15 yr | 352 | Beacon Point, TX |
| Jul 20, 2026 | IREN | Multiple AI developers (GPU cloud) | $2.8B | ~4 yr avg | Not disclosed | IREN portfolio |
| Jul 28, 2026 | Core Scientific | AMD | $14.0B | 15 yr | ~530 | Pecos, Hunt, Muskogee, Auburn, Dalton |
| Aug 10, 2026 | Riot | Frontier AI lab, reported as Anthropic | $9.1B | 20 yr | 191 | Rockdale, TX |
| Sep 25, 2026 | Cipher Digital | Barber Lake extension (Fluidstack, then a leading AI lab) | +$5.2B | 10 to 20 yr | No new MW | Barber Lake, TX |
Two further transactions are excluded from the totals. TeraWulf’s Abernathy, Texas joint venture with Fluidstack (168 MW, about $9.5 billion over 25 years, announced October 2025) is being sold: TeraWulf agreed to sell its 50.1% interest for about $530 million. Galaxy’s Helios campus in Texas, leased to CoreWeave on 15-year terms with Galaxy guiding to more than $1.2 billion of average annual revenue, and Applied Digital ($31 billion and 1,200 MW contracted as of May 2026) are shown only as reference points because neither is a listed bitcoin miner in the same sense.
Company totals and pipelines
Where a company reports an aggregate, we use it. Where it does not, we sum the disclosed contracts. Pipeline figures are company statements and are not comparable across issuers, since some quote gross utility power and others critical IT.
| Company | Contracted value | Contracted MW | Stated pipeline or power | As of |
|---|---|---|---|---|
| TeraWulf | $26.8B (sum) | 839 IT | 2.1 GW development pipeline; Muskie, KY up to 1 GW; Morgantown, MD up to 1 GW | Aug 5, 2026 |
| Hut 8 | $26.6B (reported) | 949 IT | 8,660 MW total pipeline, 1,330 MW under construction | Aug 4, 2026 |
| Core Scientific | $24.2B ($24B reported) | ~1,120 (1.1 GW leased) | AMD may reserve up to 2 GW more | Jul 28, 2026 |
| Cipher Digital | $16.6B (sum) | 700 gross | ~4.4 GW pipeline, ~5.3 GW target portfolio; 900 MW Apollo option | Sep 25, 2026 |
| IREN | $15.9B (sum of disclosed) | 260 IT disclosed | $4B contracted ARR; 0.3 GW IT in 2026, 0.8 GW in 2027; over 5 GW pipeline incl. 2 GW Sweetwater | Aug 27, 2026 |
| Riot | $9.8B (reported) | 241 IT | Multi-gigawatt Rockdale interconnection | Aug 10, 2026 |
| CleanSpark | $6.6B | 175 IT | Non-binding LOI on 885 MW Texas portfolio | Jul 14, 2026 |
| MARA | None signed | 0 | 4.8 GW expected after pending acquisitions | Aug 6, 2026 |
| Bitfarms (Keel) | None signed | 0 | Panther Creek 350 MW; ~2 GW Pennsylvania applications | Aug 10, 2026 |
Core Scientific and CoreWeave: the merger that did not close
CoreWeave’s proposed all-stock acquisition of Core Scientific, valued at about $9 billion with an exchange ratio of 0.1235 CoreWeave shares per Core Scientific share, failed when Core Scientific shareholders voted it down at a special meeting. The merger agreement was terminated on October 30, 2025, after opposition led by the largest shareholder, Two Seas Capital, and a negative recommendation from proxy adviser ISS. Both companies said the commercial relationship would continue. Core Scientific has since diversified: the AMD agreement signed in July 2026 roughly doubled its leased AI capacity to 1.1 GW, reducing CoreWeave’s share of its contracted value to about 42% on our arithmetic.
Economics: revenue per megawatt
Dividing base-term value by term and critical IT megawatts gives a simple average annual revenue per MW. For powered-shell and colocation leases the range is narrow: CoreWeave at Core Scientific about $1.44 million, Fluidstack at Lake Mariner about $1.86 million, Hut 8’s Beacon Point leases about $1.86 million, Core Scientific’s AMD deal about $1.76 million, CleanSpark about $1.89 million, and the two Anthropic-linked 20-year leases at TeraWulf and Riot about $2.37 million to $2.38 million.
IREN is a different model. As a GPU cloud provider it buys the hardware, so the Microsoft contract equates to about $9.7 million per MW per year and the Nvidia contract about $11.3 million. IREN says recent three-year contracts exceed $20 million of total revenue per MW with roughly two-year payback, but the $5.8 billion Dell equipment order behind the Microsoft deal (about $29 million per MW) shows how much capital sits behind that revenue.
Mining is the comparison point. Hashrate Index’s September 28, 2026 roundup put hashprice at $39.87 per PH/s per day, with bitcoin near $83,479, and estimated revenue of $138 per MWh for fleets under 14 J/TH, $100 per MWh for 14 to 19 J/TH and $75 per MWh for 19 to 25 J/TH. Annualised, that is about $0.66 million to $1.21 million of gross revenue per MW before power costs, versus lease revenue that is largely net of power under triple-net structures. Riot guides to average annual NOI of $365 million to $411 million on roughly $455 million of average rent, an 80% to 90% margin, with no exposure to the halving cycle or hashprice.
Capex and financing
- Build cost. TeraWulf guides to $8 million to $10 million per critical IT MW; Core Scientific’s AMD sites are estimated at $11 million to $12 million per MW. At those rates the roughly 4 GW under contract implies tens of billions of construction spend over 2026 to 2028.
- Project debt. Hut 8 has closed $7.5 billion of project notes: $3.25 billion for River Bend and $4.25 billion (Baa2) for Beacon Point phase 1. Cipher has $1.733 billion, $2.0 billion and $810 million of senior secured notes. Riot arranged a $573 million Morgan Stanley interim facility pending investment-grade financing.
- Convertibles. TeraWulf issued $1.0 billion and $1.025 billion of converts plus $3.2 billion of 7.75% secured notes in 2025. Cipher has a $1.3 billion zero-coupon convert. Bitfarms raised $458 million of converts in June 2026.
- Hyperscaler credit support. Google backstops Fluidstack rent at TeraWulf ($3.2 billion total commitment, about 14% pro forma equity via warrants), Cipher ($1.4 billion plus $333 million, 5.4% stake) and Hut 8’s River Bend lease. Nvidia received a warrant for up to 30 million IREN shares at $70.
- GPU finance. IREN has $6.4 billion of GPU financing: $3.6 billion investment-grade at 6.0% tied to Microsoft and $2.8 billion led by Blue Owl and PIMCO-advised investors, plus customer prepayments of 45% to 55% of GPU capex.
Risks
- Tenant concentration. Leases directly with or reported as Anthropic total $28.1 billion (22% of the $126.5 billion), rising to $35.1 billion (28%) including Hut 8’s Fluidstack lease tied to Anthropic’s build-out. Fluidstack-related leases total $17.5 billion. Several 2026 tenants are unnamed, which limits outside credit assessment.
- Execution. Most 2026 contracts deliver in the second half of 2027 or 2028 (TeraWulf Hawesville early 2028, Riot full 191 MW by June 2028, Beacon Point phase 2 in Q2 2028). Rent starts only on delivery, and Cipher bears the first $359.3 million of Barber Lake cost overruns.
- Power and interconnection. Pipeline figures rely on approvals not yet granted, including ERCOT large-load processes at Sweetwater and Matagorda County and FERC approvals at Morgantown and Long Ridge.
- Leverage and dilution. Warrant liabilities of $1.8 billion at TeraWulf and $1.98 billion at Core Scientific, and multi-billion secured debt stacks, mean equity holders sit behind lenders until projects are cash generative.
Methodology
Period: contracts announced from June 2024 through September 30, 2026, with data as of the latest company release cited (up to September 28, 2026 for market data). Sources are company press releases, SEC 8-K exhibits and quarterly results, supplemented by trade press (DatacenterDynamics, The Block, Data Center Frontier) where filings lacked detail. Contract value is base-term value as disclosed, excluding renewals. Company totals use the reported aggregate where available (Hut 8, Riot, Core Scientific as the sum of CoreWeave and AMD) and otherwise our python sum of disclosed contracts: TeraWulf ($19.0B + $6.7B + $1.1B), Cipher ($11.4B reported at March 31, 2026 plus the $5.2B extension) and IREN ($9.7B + $3.4B + $2.8B). Revenue per MW per year equals value divided by term and critical IT MW; it ignores escalators and ramp timing. Mining revenue per MW multiplies Hashrate Index’s per-MWh estimates by 8,760 hours. Megawatt totals mix critical IT and gross power (Cipher reports gross) and should be read as approximate. Limitations: values for Cipher’s March 2026 lease (implied at about $2.1B by subtraction) and IREN’s July batch MW are undisclosed; the Riot tenant is identified as Anthropic by media reports, not the company. Not investment advice.
Sources
- Hut 8 second quarter 2026 results (Aug 4, 2026)
- TeraWulf Q2 2026 results, SEC 8-K (Aug 5, 2026)
- Riot Platforms Q2 2026 release and lease disclosure, SEC 8-K (Aug 10, 2026)
- Core Scientific Q2 2026 results and AMD agreement, SEC 8-K (Jul 28, 2026)
- Core Scientific: termination of CoreWeave merger agreement (Oct 30, 2025)
- Cipher Digital business update, SEC 8-K (Aug 4, 2026)
- Cipher Digital Barber Lake lease extension release (Sep 25, 2026)
- IREN FY26 results (Aug 27, 2026)
- CleanSpark $6.6B Sandersville lease (Jul 14, 2026)
- Hashrate Index roundup, hashprice and revenue per MWh (Sep 28, 2026)
Questions on this report
Did Core Scientific's merger with CoreWeave close?
No. Core Scientific shareholders rejected the roughly $9 billion all-stock deal and the merger agreement was terminated on October 30, 2025. CoreWeave remains a tenant on about 590 MW under 12-year contracts worth about $10.2 billion.
How much AI and HPC contract value have listed bitcoin miners announced?
About $126.5 billion of base-term value across TeraWulf, Hut 8, Core Scientific, Cipher Digital, IREN, Riot and CleanSpark as of September 2026, by BlockWest's sum of company disclosures, excluding renewal options and divested contracts.
Why do miners prefer AI leases to bitcoin mining?
Colocation leases in this tracker average about $1.4 million to $2.4 million of revenue per critical IT MW per year on 10 to 20 year terms, versus roughly $0.66 million to $1.21 million of gross mining revenue per MW at late-September 2026 hashprice, with no halving or hashprice exposure.
BlockWest Research reports are built from public filings, company disclosures and third-party data providers named in each report. Figures are point-in-time and are not updated after publication unless noted. This is research and commentary, not investment advice. Spotted an error? Email the desk via the contact page.
