Research / Tracker
Tracker · Q3 2026

The gigawatt ledger: tracking AI data center campuses and power deals

Eleven top US AI campuses plan 14.4 GW of IT power, but only 4.1 GW runs today; we track the campuses, power deals and grid limits as of October 2026.

BlockWest Research·Published October 5, 2026·9 min read·Data as of Oct 28, 2026

Key findings

  • Eleven of the largest US AI campuses tracked by Epoch AI sum to 14,339 MW of planned IT power, but only 4,445 MW (31.0%) was operating as of late October 2026.
  • Epoch’s estimated capital cost for those eleven campuses at full build is $543.0 billion, about $37.9 billion per planned gigawatt of IT power (our calculation).
  • The four Oracle-hosted Stargate campuses in the sample account for 4,962 MW of planned IT power, yet only Abilene (618 MW as of October 2026) is running.
  • Four signed nuclear deals with existing or restarted plants (Talen/Amazon, Constellation/Meta Clinton, Constellation/Microsoft Crane, NextEra/Google Duane Arnold) cover 4,491 MW, and Google’s October 6, 2026 Constellation agreement adds 890 MW of uprates plus 2,700 MW of existing PJM supply, while advanced nuclear options from Meta, Amazon and Google add roughly 9.9 GW, mostly after 2030.
  • ERCOT faced an estimated 474 GW of large-load interconnection requests in August 2026, about 90% of them data centers, prompting a governor-ordered audit.
  • GE Vernova reported 122 GW of gas turbine backlog plus slot reservations on October 28, 2026 (up from 116 GW in July), against the roughly 20 GW of annualized output it cited in July, making turbines a gating input for on-site power.
14.3 GWplanned IT power, 11 campuses, Oct 2026
4.4 GWof that operating, Oct 2026
$543Best. capex at full build, Oct 2026
474 GWERCOT large-load requests, Aug 2026

The campus ledger

The AI build-out has moved from individual data halls to campuses measured in gigawatts. This tracker uses Epoch AI’s satellite-based data center directory as a common yardstick, because company announcements mix facility power, grid interconnection and long-range ambitions. Epoch reports IT power (the load available to servers), which is typically below a site’s headline facility or grid figure. We show both where a company has published a headline number.

CampusLocationOwner / tenantAnnounced capacityEpoch planned IT powerOperating IT power (Oct 2026)Epoch est. capex at full buildStatus
Microsoft Fairwater WisconsinMount Pleasant, WIMicrosoft$7B+ committed (two data centers)2,263 MW (Q2 2028)369 MW$85.7BBuilding 1 live April 2026; buildings 3 to 11 projected May 2028
Project Rainier (New Carlisle)New Carlisle, INAmazon / Anthropic2.2 GW, $11B1,925 MW (Q1 2028)1,037 MW$72.9BOperating on Trainium2; Trainium3 expansion planned
Stargate New Mexico (Project Jupiter)Doña Ana County, NMOracle, STACK / OpenAI2.2 GW1,750 MW (end 2028)0 MW$66.3BUnder construction since October 2025
Meta HyperionRichland Parish, LAMeta (Blue Owl 80% JV)5 GW+, $50B+ infrastructure1,632 MW (Q1 2028)0 MW$61.8BRoofs done April 2026; first phase January 2028
Colossus 2Memphis, TN areaSpaceX/xAINot formally disclosed1,531 MW (Q1 2027)946 MW$58.0BThree phases live; building 3 due February 2027
Stargate Shackelford (Frontier)Shackelford County, TXOracle, Vantage / OpenAI2.0 GW1,400 MW (Nov 2028)0 MW$53.0BBuildings online August 2027 to November 2028
Meta PrometheusNew Albany, OHMeta1 GW1,022 MW (Q3 2028)471 MW$38.7BOperating, including tent buildings
Stargate MichiganSaline Township, MIOracle, Related Digital / OpenAI1.4 GW988 MW (Q4 2028)0 MW$37.4BEarly groundwork; DTE supply approved
Stargate AbileneAbilene, TXOracle, Crusoe / OpenAI1.2 GW (600 MW expansion dropped)824 MW (Q4 2026)618 MW$31.2BBuildings 1 to 6 live (5 and 6 per Oracle, September 2026); 7 and 8 estimated operational November 1, 2026
Microsoft Fairwater AtlantaFayetteville, GAMicrosoft (QTS)Not disclosed636 MW636 MW$24.1BFully built; buildings 3 and 4 live June 2026
Google Pryor (North)Pryor, OKGoogleNot disclosed368 MW368 MW$13.9BBuilding 2 live September 2026

Summing Epoch’s figures, the eleven campuses reach 14,339 MW of planned IT power, of which 4,445 MW was operating in late October 2026. Three campuses (Fairwater Atlanta, Pryor North and, nearly, Colossus 2) are mostly built; the rest of the pipeline lands in 2027 and 2028. Several announced projects sit outside Epoch’s detailed coverage: Stargate Milam County, Texas (SB Energy, 1.2 GW per Epoch’s April 2026 review; OpenAI had cited 1.5 GW), Stargate Port Washington, Wisconsin (Vantage, 1.3 GW), the Lordstown, Ohio SoftBank site (under 0.3 GW of visible data center build) and CoreWeave’s $6 billion Lancaster, Pennsylvania campus (100 MW initial, up to 300 MW).

Planned IT power by campus (MW, Epoch AI, as of November 2, 2026)
Fairwater Wisconsin2,263 MW
Rainier, New Carlisle1,925 MW
Stargate New Mexico1,750 MW
Meta Hyperion1,632 MW
Colossus 21,531 MW
Stargate Shackelford1,400 MW
Meta Prometheus1,022 MW
Stargate Michigan988 MW
Stargate Abilene824 MW
Fairwater Atlanta636 MW
Google Pryor North368 MW

Announced versus measured

The gap between headline and measured capacity is material. Meta has described Hyperion as scaling to 5 GW and raised its infrastructure budget to more than $50 billion in July 2026 (from $10 billion in 2024 and $27 billion in 2025), but Epoch’s current build plan shows 1,632 MW of IT power by early 2028. Amazon’s 2.2 GW figure for New Carlisle is a total power draw; Epoch’s planned IT power is 1,925 MW. Stargate shows the same pattern: OpenAI said in September 2025 that its sites brought planned capacity to nearly 7 GW and over $400 billion of investment over three years, while the four Oracle-hosted campuses Epoch tracks in detail total 4,962 MW of IT power, with $187.9 billion of estimated capex, and only Abilene’s 618 MW is running (as of October 2026).

Plans also contract. In March 2026 Oracle and OpenAI dropped a 600 MW expansion at Abilene that would have taken the site toward 2 GW, citing power arriving roughly a year later than the hardware cycle; the core 1.2 GW campus remained on schedule and the broader 4.5 GW Oracle agreement was unaffected. Readers should treat headline gigawatts as options and Epoch’s dated build plans as the better guide to near-term supply.

The power deal book

Hyperscalers are contracting for firm power on two tracks: existing or restarted nuclear plants that can deliver this decade, and advanced reactors and on-site gas that come later or carry execution risk.

DealBuyerCapacityTerm / timingType
Talen Susquehanna PPAAmazon1,920 MWThrough 2042, ramping to 1,680 to 1,920 MW by 2032; about $18B revenueExisting nuclear, front of meter
Constellation ClintonMeta1,121 MW (+30 MW uprate)20 years from June 2027Existing nuclear relicensing
Constellation Crane (ex Three Mile Island Unit 1)Microsoft835 MW20 years; restart targeted 2027; $1B DOE loanNuclear restart
NextEra Duane ArnoldGoogle615 MW25 years; power by early 2029Nuclear restart
Constellation uprates and PJM supply (announced October 6, 2026)Google890 MW of uprates at 11 reactors, plus 2,700 MW of existing output20 years for uprates (first by 2028, all by end 2032); 15 years for existing supplyExisting nuclear uprates and supply
TerraPower NatriumMetaUp to 2.8 GW (+1.2 GW storage)Two funded units, rights to six more, up to eight by 2035Advanced nuclear
Oklo Aurora, Pike County, OHMetaUp to 1.2 GWAs early as 2030Advanced nuclear
Vistra uprates (Perry, Davis-Besse, Beaver Valley)Meta433 MW of upratesEarly 2030sUprates (part of 6.6 GW Meta package)
Kairos PowerGoogleUp to 500 MWFirst unit 2030, complete by 2035Advanced nuclear (SMR)
X-energyAmazonMore than 5 GWBy 2039; first 320 MW at Energy NorthwestAdvanced nuclear (SMR)
Hyperion supply (Entergy)Meta10 new power plants; 2,262 MW of turbines per Epoch; 1.5 GW solar and storagePower stations operational December 2026 per EpochUtility gas plus solar
Stargate New Mexico microgridOracle / OpenAIUp to 2.45 GW of Bloom fuel cellsWith campus build to 2028On-site fuel cells

The four existing or restart nuclear contracts total 4,491 MW, or 8,081 MW including Google’s October 2026 Constellation agreement (890 MW of uprates and 2,700 MW of existing supply). The advanced nuclear options (TerraPower, Oklo, Vistra uprates, Kairos, X-energy) add roughly 9.9 GW in announced maximums, nearly all after 2030. That timing gap explains why the near-term campus pipeline leans on gas: Colossus 2 runs on gas turbines in Mississippi with on-site batteries, Prometheus on dedicated gas plants, Abilene on turbines plus a 1 GW substation, and Hyperion on new Entergy generation.

Grid queues and ERCOT large loads

Lawrence Berkeley National Laboratory counted 2,061 GW of generation and storage in US interconnection queues at the end of 2025, down 10% from the prior year and from a peak of nearly 2,600 GW at end 2023. Gas was the exception, with 253 GW queued, up 86% year on year. Only 13% of capacity requested from 2000 to 2020 had reached operation by end 2025, and the median project took more than three years to sign an interconnection agreement.

The load side is now the bottleneck in Texas. ERCOT faced an estimated 474 GW of large-load interconnection requests as of August 2026, about 90% of them data centers. Governor Greg Abbott ordered an audit of data centers in the queue covering on-site generation, water and public incentives, and ERCOT delayed its Batch Zero study, which follows a new large-load process approved in June 2026. New York imposed a one-year data center approval moratorium in July 2026. In PJM, Constellation has asked FERC to transfer capacity interconnection rights from its Eddystone plant to Crane after PJM analysis suggested the restart might not connect until 2031.

Demand projections

Source (date)ScopeBaselineProjection
LBNL for DOE (Dec 20, 2024)US data centers176 TWh in 2023, 4.4% of US electricity325 to 580 TWh by 2028, 6.7% to 12%
IEA, Energy and AI (Apr 10, 2025)Global data centersAbout 415 TWh in 2024945 TWh by 2030; US data centers drive almost half of US demand growth
EIA STEO (Jul 7, 2026)Total US consumption4,195 billion kWh in 2025 (record)4,269 billion kWh in 2026, 4,399 billion kWh in 2027; commercial sales exceed residential in 2026

The LBNL range implies US data center consumption growing 85% to 230% between 2023 and 2028, and the IEA path implies global data center demand rising about 2.3 times from 2024 to 2030 (our calculations). EIA does not break out data centers in the figures cited but attributes the record demand path largely to AI and crypto data centers.

Risks to the ledger

  • Interconnection timing. Queue durations above three years and cases like Crane’s possible 2031 connection can strand campuses that are otherwise built.
  • Equipment scarcity. GE Vernova’s 122 GW of gas turbine backlog and reservations (as of October 28, 2026) against about 20 GW of annualized output (rising to 24 GW in 2028 and 30 GW in 2030) limits how fast on-site gas can scale.
  • Policy pushback. The Texas audit and New York moratorium show state willingness to slow large loads over reliability, water and subsidy concerns.
  • Hardware cycle mismatch. The Abilene expansion was dropped partly because power would arrive after a GPU generation turned over.
  • Financing concentration. Oracle reportedly carries more than $100 billion of debt tied to Stargate commitments, and Hyperion is 80% held by Blue Owl, placing off-balance-sheet and credit risk on a small set of counterparties.
  • Advanced nuclear execution. Most of the roughly 9.9 GW of advanced nuclear options depend on first-of-a-kind reactors arriving between 2030 and 2039.

Methodology

Campus figures come from Epoch AI’s AI data center directory entries, checked November 2, 2026 (latest entry update October 28, 2026). Epoch estimates IT power and capital cost from satellite imagery, permits and disclosures; capex includes compute hardware and is Epoch’s estimate, not a company figure. Announced capacity and investment come from company releases and press reports, with dates in Sources. We selected the largest US campuses with Epoch detail pages, plus announced sites without them listed in text only. Totals, the operating share (4,445 of 14,339 MW), capex per planned gigawatt ($543.0B divided by 14.339 GW), the Stargate subtotal, nuclear subtotals and growth multiples were computed in Python from the cited inputs. Chart bar lengths are percentages of the largest value (2,263 MW). Advanced nuclear totals sum announced maximums and are not delivery forecasts. Limitations: IT power and facility power are not directly comparable; Epoch projections can change as plans shift; the ERCOT figure covers requests, not committed load; and some deal terms (prices, Vistra existing-plant PPA volumes) were not verified.

Sources

Get BlockWest Research in your inbox

New reports, trackers and scorecards on markets, AI and digital assets, sent when they publish.

Subscribe to the newsletter

Questions on this report

What is the largest AI data center campus in this tracker?

By Epoch AI's planned IT power, Microsoft Fairwater Wisconsin leads at 2,263 MW by 2028. By headline announcement, Meta Hyperion is the largest at 5 GW or more, though Epoch's current build plan shows 1,632 MW of IT power by early 2028.

How much of the planned capacity is actually running?

Across the eleven campuses tracked, 4,445 MW of 14,339 MW planned IT power (31.0%) was operating as of late October 2026, based on Epoch AI data.

Why are hyperscalers signing nuclear and gas deals?

Grid interconnection takes years and large-load queues are congested. Existing and restarted nuclear plants (4,491 MW in four signed deals, plus 3,590 MW of uprates and existing supply in Google's October 2026 Constellation agreement) supply firm power this decade, while on-site gas and fuel cells bridge the gap until advanced reactors arrive after 2030.

BlockWest Research reports are built from public filings, company disclosures and third-party data providers named in each report. Figures are point-in-time and are not updated after publication unless noted. This is research and commentary, not investment advice. Spotted an error? Email the desk via the contact page.